Skip to content

Permits and regulations

What permit you need to renovate in Marbella and how long it takes

· 2 min read

For interior work that does not affect the structure, the façade or the use of the property, a responsible declaration is usually enough in Costa del Sol municipalities, and it allows work to start almost immediately. If the structure is altered, openings are made in load-bearing walls or the façade is changed, a major works permit with a project drawn up by a qualified technician is required, and there you should expect weeks or months of processing.

Which procedure applies to you

ProcedureWhen it appliesUsual timescale
Responsible declarationInterior work not affecting structure, façade, window openings or use. Changing floors, tiling, bathroom, kitchen, installations and paint.Work can start on submission, unless the council raises a query.
Minor works permitSomewhat larger interior work, or work affecting minor common elements, depending on each council's criteria.From a few weeks to a couple of months.
Major works permitStructural changes, openings in load-bearing walls, façade alterations, extensions or change of use.Months. Requires a technical project and professional approval.
The specific criteria are set by each council: Marbella, Estepona, Mijas and Fuengirola are not identical. It is worth confirming case by case.

What is usually required

  • The council's form, completed and signed by the owner.
  • A detailed quote for the work, which determines the municipal fee.
  • A description of the works and, depending on the case, drawings of the existing and proposed layouts.
  • Proof of payment of the fee and the construction tax (ICIO).
  • For major works, a project drawn up by a qualified technician and site supervision.

What happens if you renovate without a permit

The council can order the work to stop and impose a fine. In addition, unauthorised work can cause problems when selling the property or arranging insurance. For interior renovations the risk is usually low, but a single complaint from a neighbour is enough to trigger an inspection.

And the community of owners

This is a separate permission from the municipal one, and it is also required. The community must authorise anything affecting common elements: the façade, windows facing outwards, communal soil pipes or terrace enclosures. It is requested before starting; doing it halfway through is the fastest way to have the work stopped.

On our projects we handle the paperwork and it is included in the quote, so the only formality left for you is signing.

Free visit and quote

Tell us what you want to renovate.

Message us on WhatsApp with the area, what you want to do and when. We reply within minutes between 9am and 8pm and propose a day for the visit.